Associated with the expansion of Motorring 3 -
Frederikssundmotorvejen M12, NNC Danmark A/S used 10 pot-bearings, 2
guided and 8 loose guided for
3500kN, these bearings were intergrated in week 14, the
engineering contractor NCC. The highway bridge
were finished in August 2010.
Contractor: Vejdirektoratet
Enginering contractor: NCC Danmark A/S